Backyard BuildingsStorage, workshop and garden concepts.Why SteelHow the framing and wall system work.Cost CalculatorBuild a preliminary project range.Regions & City GuidesExplore Northern California, Central Valley and Southern California.Knowledge CenterCosts, permits, models, systems and planning guides.FAQAnswers about cost, permits, licensing, and steel framing.ContactReach the ADU California Inc. team.
(650) 400-7606Check my property
(650) 400-7606
  1. Home
  2. /
  3. FAQ

Questions and answers

ADU questions, answered

These answers restate what is already published on adu.zone or in the official sources linked below. They are planning information, not a permit decision, a bid, or legal advice. Confirm the current rule with the city that has jurisdiction over the property.

ADU CALIFORNIA INC · 84 W Santa Clara St, Suite 700, San Jose, CA 95113 · (650) 400-7606 · CSLB #1163442

Homeowner questions

Start with what is known.

If you already have an address, a preliminary property check or a consult is the next step. Neither one is a permit, a price, or a construction schedule.

Check my propertyCost calculator (650) 400-7606
01

Can every California property support an ADU?

No single online check can guarantee that. Zoning, parcel geometry, setbacks, existing structures, easements, utilities, access, hazards, local review, and project-specific engineering can all affect the final answer.

02

Are the ADU models permit-ready for any property?

No. Models with defined footprints are starting concepts; the two-storey design study still needs a measured plan. Final architecture, engineering, foundation, energy, utility, fire, and permit documents must be adapted and approved for the specific site.

03

How much does an ADU cost?

Cost depends on model size, design changes, finishes, utilities, access, grading, demolition, jurisdiction, and site conditions. The calculator provides an early planning range, not a bid or contract price.

04

How long do permitting and construction take?

For a straightforward detached steel-frame ADU, our current planning model allows 1–2 months for design and engineering, 2–4 months for permitting, and 7–10 months for construction (10–16 months overall). These are preliminary planning allowances, not guaranteed or measured completion times. Corrections, agency workload, utility upgrades and difficult site conditions can extend the schedule; we confirm a project-specific schedule after review.

05

What does ADU California Inc. coordinate?

The project path can include property review, model selection, design, engineering coordination, permitting, steel-frame information, site preparation, construction, inspections, and closeout. The exact contracted scope must be confirmed for each project.

06

How much does an ADU cost in California?

Independent published data for a modeled 660 sq ft one-story ADU (JLC / Zonda 2025 Cost vs. Value) lists job costs of $203,481 in San Francisco, $178,536 in Los Angeles, $168,400 in Sacramento, $181,004 for the Pacific region average, and $166,406 for the national average. Those figures are modeled construction job costs for a defined project; they exclude land and may not include all permit, utility, or site costs. ADU California Inc. also publishes steel-frame planning ranges by model footprint, generated from the same model data used on the models pages. Those ranges are preliminary, not a bid or contract price, and site-specific work and utility upgrades may add cost. See the California ADU cost guide for the published table, model planning ranges, and the official sources. For San Jose fee rules and budget drivers, see the San Jose ADU cost guide.

07

Are impact fees charged on a small ADU?

Under California law, an ADU with 750 square feet or less of interior livable space is exempt from impact fees from local agencies, special districts and water corporations; larger ADUs are charged proportionately to the primary dwelling (Gov. Code § 66311.5). Source: HCD ADU Handbook, March 2026.

08

How fast must a city act on an ADU permit?

A permitting agency must approve or deny a complete ADU application within 60 days when there is an existing dwelling on the lot (Gov. Code § 66317). Source: HCD ADU Handbook, March 2026.

09

Why steel framing?

ADU California Inc. uses cold-formed steel framing for its ADU models. The frame material is noncombustible, dimensionally consistent, and is not a food source for termites. Fire performance still depends on the complete code-compliant assembly, and permits, utilities, foundations, inspections, weather, and finish work still govern the full project schedule. See Why Steel for the full explanation.

10

How long does an ADU take?

For a straightforward detached steel-frame ADU, our current planning model allows 1–2 months for design and engineering, 2–4 months for permitting, and 7–10 months for construction (10–16 months overall). These are preliminary planning allowances, not guaranteed or measured completion times. Corrections, agency workload, utility upgrades and difficult site conditions can extend the schedule; we confirm a project-specific schedule after review. The ADU building timeline guide explains what can change that path, including the 60-day review clock, site work, and inspections.

11

Can I check my property?

Yes. You can start a preliminary property check. The check is preliminary: it does not establish eligibility, a final cost, or a construction schedule. Current records, local requirements, site conditions, and professional review control the result.

12

Is ADU California Inc. licensed?

Yes. ADU CALIFORNIA INC holds California CSLB license #1163442.

Let’s build your ADU

Your property.
Your next chapter.

Explore the possibilities for your California property.

Check my property
Architectural concept of a modern California ADU in a landscaped garden, shown in natural daylight
Design concept

Let’s talk about your project.

(650) 400-7606info@adu.zone

ADU CALIFORNIA INC

San Jose office

84 W Santa Clara St, Suite 700
San Jose, CA 95113

Open 24/7

(650) 400-7606Get directions

Walnut Creek office

1990 N California Blvd, 8th Floor
Walnut Creek, CA 94596

Open 24/7

(650) 400-7606Get directions
ADU CALIFORNIA INC
  • Facebook
  • Visit us on Industry Oversight
FAQCalifornia ADU costKnowledge Center
Legal & disclosuresPrivacyTerms of useAccessibility
CSLB #1163442

© 2026 ADU CALIFORNIA INC. All rights reserved.

San Jose · Walnut Creek · California